« Back to News & Notices

Downtown Streetscape Project

6/2/2025

Here is the latest update on the streetscape work provided to the Four Oaks Chamber by: Carter Loverrn, Project Manager for Fred Smith Company.

Last week: Temporary signal poles installed at the intersection of N. Main and Wellons, Duke Energy continuing to work on underground and business conversions, Spectrum on site Friday to start moving their overhead lines

This week: Duke energy continues service conversions and underground work, Spectrum continuing to move their overhead supply, Brightspeed mobilizes to begin moving their overhead lines and remove old poles.

Next Week: Bright speed finishing up their overhead relocation, if complete FSC will mobilize and begin digging retaining wall footers